Construction start and end

To prepare for the Jock's Lodge improvement scheme, work in Skidby started on 31 July 2023 and completed at the end of 2023. These works included:

  • Moving the current bus stop on the A164 to Main Street in Skidby, making it easier for passengers to get to the bus stop.
  • Constructing a new roundabout at the junction of Main Street and Beverley Road, Skidby.

The main works for the Jock's Lodge improvement scheme commenced on 08 January 2024 and is expected to complete by the end of 2026

Mar
2020
Planning application

The council submitted a planning application for the scheme

Jul
2020
Planning permission

Planning permission for the scheme was granted

Jan
2021

Compulsory Purchase Order and Side Roads Order granted

May
2023
Accommodation works

Appointed Contractor to undertake accommodation works

Nov
2023
Contractor appointed

Appointed Contractor to undertake construction - GRAHAM

Jan
2024
Work commences

Work on the A164 & Jock’s Lodge Junction improvement scheme commenced

Subscribe to Jock's Lodge Newsletter

Join our newsletter and stay updated on the latest Jock's Lodge developments

We use GovDelivery to send you emails, which is secure and you can choose to stop receiving emails at any time.

Subscribe to the newsletter

Alerts